sbank-detail-projects [options] [ ... ]

Detail project information.

NOTE: 1. The list of arguments are optional 2. you can also enter list by using the -p option multiple times 3. regardless, both are optional, and you can get detail project info using the option filters below

OPTIONS

--version

show program's version number and exit

-h, --help

show this help message and exit

-a ALLOCATION_ID, --allocation-id=ALLOCATION_ID

filter on allocation id

-f FIELD_INFO, --field-to-display=FIELD_INFO

FIELD_INFO is [:], for available fields enter -f? or -f "?", to add fields enter -f "+ [:] ..."

-n NUM_FIELDS_TO_DISPLAY, --num-fields-to-display=NUM_FIELDS_TO_DISPLAY

set number of fields to display

-p PROJECT, --project=PROJECT

filter on name or id, DO NOT MIX, enter 'all' to get all, wild cards '*' is allowed but only on names

-r RESOURCE, --resource=RESOURCE

filter on name or id, DO NOT MIX, enter 'all' to get all, wild cards '*' is allowed but only on names

-u USER, --user=USER

filter on name or id, DO NOT MIX, enter 'all' to get all, wild cards '*' is allowed but only on names

-w "FIELD_INFO", --field-width

"FIELD_INFO" FIELD_INFO is :, for available fields enter -w? or -w "?"

-E END, --end=END

[OPER1][...[OPER2]], where the operators OPER1 and OPER2 can be one of the following:

  • ge, gt, le, lt, eq or >=, >, <=, <, ==.

Operator Defaults:

  • OPER1 is 'lt' for single date entry, OPER1 and OPER2 are 'ge' and 'lt', respectively, for range date entry.

Date Parsing Precedence: - YEAR then MONTH then DAY, i.e., 121101 is parsed as YYMMDD, hence Nov. 1, 2012

-H, --human-readable

abbreviate numbers and use unit suffixes: K (thousands), M (millions), G (billions), T (trillions) ...

-I, --get-inactive

get inactive allocations

-S START, --start=START

[OPER1][...[OPER2]], where the operators OPER1 and OPER2 can be one of the following:

  • ge, gt, le, lt, eq or >=, >, <=, <, ==.

Operator Defaults:

  • OPER1 is 'ge' for single date entry, OPER1 and OPER2 are 'ge' and 'lt', respectively, for range date entry.

Date Parsing Precedence:

  • YEAR then MONTH then DAY, i.e., 121101 is parsed as YYMMDD, hence Nov. 1, 2012

--debug=DEBUG_LEVEL

SILENT, MUCH_LESS, LESS, MORE, VERBOSE, DEBUG, DEBUG1, DEBUG2

--all-charges

only show list info that have charges regardless of project/user relationship

--no-commas

remove commas from comma separated thousands

--no-header

do not display the header

--no-rows

do not display the row data

--no-sys-msg

do not display system message

--no-totals

do not display the totals